Pole attachment deadline calculator
Every deadline on a pole attachment application, from one date
Enter the date an application went to the utility and how many poles it covers. You get every date the rule gives the utility, the day each kind of self-help opens, and what you have to do yourself. Free, no sign-up. We are not the FCC or a state commission, and this is not legal advice.
Before you rely on these dates
- The FCC rule and most state rules cover investor-owned power companies and telephone companies. Electric cooperatives, municipal utilities, public utility districts and railroads are outside the federal statute (47 U.S.C. 224(a)(1)); some states cover them separately, for example North Carolina (G.S. 62-350), Virginia (Va. Code 56-466.1) and Washington (RCW 54.04.045).
- The FCC's access rights belong to cable operators and telecommunications carriers; a broadband-only provider is not covered, which is why many fiber builders attach through a carrier affiliate.
- The FCC's 2026 changes (mid-sized and large orders, the 15-day "cannot meet" notices, estimate self-help) apply from 7 May 2026. Older applications ran on the earlier rule.
Read from 47 CFR 1.1411 as in force on 9 October 2026, the state rules named above, and the FCC's list of certified states (Public Notice DA 22-630). The rules themselves govern.
Would you use a version that watches every application?
We are deciding whether to build it. It would:
- keep every pole application in one list, by utility and state, with each deadline worked out the moment you enter the filing date,
- email you the day a utility misses a survey, estimate or make-ready date, with the self-help option it opens and the notice to send,
- check make-ready invoices against the estimate you accepted.
Planned price: $99 a month per company. If you would use it, join the early-access list. Nothing is built yet and there is nothing to pay now.